Construction NOCs
NOCs for Residential & Commercial Plots
Foundation of Basement Level NOC
- Basement area verification.
- Verification of height/ depth.
- Verification of underground water tank.
Plinth Level NOC
- Right, Left & Rear Compulsory Open Space.
- Height & area of Basement.
- Underground water tank slab level.
- Earth filling in Compulsory Open Space.
- Extra excavation material dumped in open plots.
- Height of plinth level from road level.
- Right, Left & Rear situ.
- Verification of Boundary pillar check.
Ground Floor Level NOC
- Height of slab level.
- Area of ground floor as per approval.
- Verification of front Compulsory Open Space.
- Ground floor slab projection for commercial buildings.
- Duct area as per approval.
First Floor of Subsequent Level NOC
- Height & area as per approval.
- Height & area and measurement of ducts as per approval.
Stair Tower NOC
- Area of stair tower as per approval.
- Fire fighting system.
- Main gate bottom & ramp.
- Flooring works.
- Guard room verification.
- Boundary wall height.
- External faced for comm. Buildings.
- Parapet wall height.
- Removal of debris/ cleaning of site.
Notes
- NOC visit & issuing of NOC within 15 working days.
- Visit conducted 6 to 7 working days.
- Computerized NOC issued to owner within 03 days.
Documents Required / Check List
Requirement for Stage wise NOCs (Visit Required)
- Application from owner.
- Copy of demarcation letter.
- Copy of approved Building plan (Copy of approved Deviation letter & Drawing if issued).
- Registered structure Engineer/Architect Certificate.
- Previous level NOC if obtained.
Requirement for Stage wise NOCs (No Visit Required)
- Original NOCs Slip.
- Original Demarcation Letter (only for Foundation of Basement & Plinth Level NOC).
- Photocopy of demarcation letter.
- Registered structure Engineer/Architect Certificate.
- Copy of approved Deviation letter (if required).